18th July 2019

Works progressing at Crown Street

Construction works at Ediston and Clydebuilt’s Crown Street Retail Park continue to move at pace. The contractor, Heron Brothers is wasting no time in progressing the envelope of the units and the concrete floor pours have been going well, with summer temperatures helping the drying / curing process. The target is now to get the buildings wind and watertight by the end of July allowing internal works to follow-on. Planned completion is still on target for Q1 2020.